Choose the side of the wall you are on.
Still unsure? Call 0203 129 9374 for free initial advice.
Yes, if you are working on a wall you share with a neighbour, building a new wall at the boundary, or digging foundations within 3 metres of their building (6 metres for very deep foundations). Most loft conversions and extensions on terraced and semi-detached homes are covered.
At least two months before work on a shared wall, and at least one month before a new boundary wall or excavation. We recommend serving as soon as your drawings are settled. A notice stays valid for 12 months.
Yes. You do not need a surveyor to serve a notice, and our notice generator will draft one for you. Take care with the details: a notice with errors can be invalid, which means starting the notice period again.
For shared wall and excavation notices, silence for 14 days counts as a dispute. You then write asking them to appoint a surveyor within 10 days. If they still do not, a surveyor can be appointed on their behalf so the process keeps moving.
Normally you do, as the person having the work done. That includes your neighbour's surveyor's reasonable fees. Using one agreed surveyor for both sides is usually the most economical route.
Not the notifiable parts of the work, unless your neighbour has consented in writing. Starting without consent or an award risks a court injunction and leaves you exposed to damage claims. Work that is not covered by the Act can carry on.
No. The Party Wall etc. Act 1996 is separate from planning permission and building regulations. You may need to comply with all three.
When each owner appoints their own surveyor, the two surveyors must straight away select a third surveyor in writing. The third surveyor is rarely called on. They only step in if the two surveyors cannot agree a point, or if either owner or either surveyor asks them to decide a disputed matter. Their decision is made by award and they decide who pays their fee, which normally follows who was unreasonable or who benefits from the work. With a single agreed surveyor there is no third surveyor.
Yes. Under Section 12 of the Act your neighbour can serve a written request, before you start, for you to put up security. This is a sum of money held safely, usually in a solicitor's or escrow account, to make sure their property can be made safe or put right if the work is left unfinished or damage is not repaired. It is most common for basements, deep excavations and other higher-risk work. If you cannot agree whether security is needed or how much, the surveyors decide and set the amount and terms in an award. The money stays yours and is returned once the notifiable work is complete and any damage is settled.
You have three: consent in writing; dissent and agree to one surveyor acting impartially for you both; or dissent and appoint your own surveyor. You have 14 days to reply.
Normally not. The owner carrying out the work usually pays the reasonable fees of every surveyor involved, including yours.
No. The Act gives your neighbour the right to carry out the work. Dissenting does not block it and is not an unfriendly act. It makes sure the work is governed by an award that protects your property.
It is a written and photographic record of your property before the work starts. Yes, allow it. If cracks or other damage appear later, the schedule is your proof of what was there before.
Your neighbour must put it right or pay you compensation instead, whichever you prefer. If you cannot agree on the damage or the cost, the surveyors decide.
Only where it is needed to carry out work covered by the Act, during normal working hours, and after giving you 14 days' notice (except in an emergency). The award normally sets out the access arrangements.
The work is not prevented. After 14 days a dispute is treated as having arisen, and after a further 10-day request a surveyor can be appointed on your behalf. It is better to reply and choose your own.
If you and the building owner each appoint a surveyor, the two surveyors select a third surveyor at the outset. You can ask the third surveyor directly to decide a disputed matter, for example if you believe the two surveyors are not dealing with a point or cannot agree. The third surveyor decides by award and also decides who pays their fee, so it is sensible to raise the concern with your own surveyor first.
Yes. Section 12 of the Act lets you serve a written request on the building owner, before the work begins, asking them to provide security. It protects you if the work is started and then abandoned, or if damage is caused and not put right. It is most often justified for basements, deep excavations, work that leaves your property exposed, or where the building owner is based overseas or is a company with few assets. Make the request early and through your surveyor. If the amount is not agreed, the surveyors decide it in an award, and the work cannot start until the security is in place.